Two-Week Sprint Plan Gantt Chart (Excludes Weekends)

A sprint Gantt chart turns the sprint backlog into a day-by-day plan. Scrum masters use it in planning to check that QA has something to test before the last two days; developers use it to see whose work they are waiting on.

  • sprint gantt chart
  • two week sprint plan diagram
  • mermaid gantt excludes weekends
  • agile sprint timeline
Two-Week Sprint Plan Gantt Chart (Excludes Weekends)2027-03-012027-03-022027-03-032027-03-042027-03-052027-03-062027-03-072027-03-082027-03-092027-03-10Payment retry endpoint Billing page redesign Webhook signature check Error state polish Regression run Release candidate BackendFrontendQASprint 14 plan
Open in editor → 13 linesrenders in GitHub, Notion, Obsidian

Mermaid code

gantt
    title Sprint 14 plan
    dateFormat YYYY-MM-DD
    excludes weekends
    section Backend
    Payment retry endpoint    :be1, 2027-03-01, 3d
    Webhook signature check   :be2, after be1, 2d
    section Frontend
    Billing page redesign     :fe1, 2027-03-01, 4d
    Error state polish        :fe2, after fe1, 2d
    section QA
    Regression run            :qa1, after be2, 2d
    Release candidate         :milestone, rc, after qa1, 0d

Paste this into any tool that renders Mermaid, or into the editor to change the theme and export PNG or SVG. Syntax reference: Gantt guide.

What this diagram shows

The excludes weekends line removes Saturdays and Sundays from the axis, so a 3d task starting on a Thursday ends the following Monday. Backend and frontend run as parallel sections starting the same day, and Regression run depends on be2 so QA begins as soon as the backend work lands. The Release candidate milestone marks the end of the sprint.

How to adapt it

  • Set the first start date to your sprint start and keep everything else relative with after.
  • Add a section Review with a one-day Sprint demo task so the ceremony shows on the chart.
  • Tag anything that must ship this sprint with crit so the red bars stand out in the planning review.
  • Add todayMarker off if the chart is a template rather than a live plan, so the vertical today line does not appear.

FAQ

Does "excludes weekends" change the duration or just the drawing?

Both. A 3d task counts three working days, so its bar stretches across any weekend in the middle. Public holidays are not excluded unless you list them as dates after excludes.

Can I show who owns each task?

Not as a column, but you can put the name in the task label (Payment retry endpoint - Ana) or use one section per person instead of per discipline.